The Industrial Park JAIP in Jericho / Palestine is undertaking a study in how to handle and treat the industrial flows from the tenants prior to discharge to the public sewer network.
The tenants, predominantly from food industry but also from the paper and packing industry, shall be looked at in detail and a overall treatment concept is required.
NWT is hired as process specialist in order to supervise a sampling and data collection program, a conceptual design phase and a budgeting phase for various technological options for each tenant and for a overall centralized industrial WWTP.
The overall plant capacity for the Phase I and II works will reach 4.000 m3/d and shall include a re-use concept.
Works started in November 2019 and shall be finished by early 2020.